Current Project Updates
Engineering & Construction Update
Water Treatment Plant Effluent Pumping and Controls
This project is currently moving towards 75 % design. Design expected to reach 75 % in July. A public meeting for the project will be held on August 13th Board of Director's meeting.
Colorado River Transmission Main Crossing
This project is nearly complete. Crews are finishing installing pipe insulation and are awaiting concrete repairs on the north side of the trail bridge. Expected completion is currently the second week of August.
Desert Road Pump Station
Design is complete and the District is now finalizing easements for the new site. Bidding for construction is expected to begin in July.
Reeder Mesa Fill Station
Fill station is now open!