Skip to main content

Mesa County 32 ½ Road Improvement Phase II

Workers in orange uniforms are using shovels to lay down asphalt on a construction site, with trees in the background.

November 13, 2025

No changes. District staff have been working with the County and the design firm, HDR, on final mark-ups for the second phase of the 32 ½ Road improvement. This phase will extend from the canal to Front Street. Another roundabout will be constructed on E ½ Road. For this phase, there are minor improvements for the water mains. Most of the work for the District will be moving water services and hydrants to accommodate the road improvement. This project is expected to be bid this winter, most likely in January, and begin construction in the spring of 2026.

Join our mailing list